Dear Experts
My clients is experiencing one issue at the time of collective release of PR using T. Code ME55. Certain PR is not showing at the time of executing with giving required input Release group and release code, however if the execution is done by giving input Release group, release code and Purchase Requisition the same document is showing. can any one tell me the possible reason for the same. Why the PR is not displaying for release using release code and release group in ME55.
Below Investigation has been done.
1. For single line item single PR is created through PS route using T.Code CJ20N.
2. Account assignment for the PR is "Q" Project Make to Order.
3. Line item not deleted for the same PR.
4. Status showing as 03 In Release (In Status tab).
5. in "Quantities/Dates" tab Closed check box in not activated.
Regards
Sanjib Naik
Message was edited by: Sanjib Naik