Mrp Date

$
0
0

Hi

 

My problem is when i create the planning indipendent requirement with transaction code MD61 for the date 20/04/2013 i create an indipendent

 

requirement that i can see in Transaction code MD04.

 

For example I have a stock of 100 unit  and an indipendent requirement that i have planned of 150 unit

 

In this case i run the transaction code MD02 and the system propose l'automatic creation of a purchase requisition

 

In this case the requirement date of the pruchase requisition is 20/04/2013 for a quantity of 50 unit

 

My problem is I would that the requirement date for this purchase requisition is 15/04/2013.

 

How i can set this parameter before?

 

Thank you so much

 

Luca