Hi
My problem is when i create the planning indipendent requirement with transaction code MD61 for the date 20/04/2013 i create an indipendent
requirement that i can see in Transaction code MD04.
For example I have a stock of 100 unit and an indipendent requirement that i have planned of 150 unit
In this case i run the transaction code MD02 and the system propose l'automatic creation of a purchase requisition
In this case the requirement date of the pruchase requisition is 20/04/2013 for a quantity of 50 unit
My problem is I would that the requirement date for this purchase requisition is 15/04/2013.
How i can set this parameter before?
Thank you so much
Luca