Hello all.
There is a quota arrangement assigned to different suppliers with rate 40/60.
Now it is necessary to be changed into another proportion or rate 20/80 but it seems it is not being corerctly calculated. One of the suppliers is being asked the first 3 months and then there are requirements fot both suppliers.
What is it necessary to do in order to have schduled lines for both suppliers from the beginning of the change? I told the user to go into MEQ2 Edit/base quantities/collect calculation; but it was done two weeks after the quota generations (I made a test in our testing client and it worked so I am not sure if the problem could be that it was not done at the same time of the new quota line).
How can I fix the problem?
Many thanks in advance and best regards.