Dear all,
We have a tipical situation in intercompany process.
We use a SchLne to already transfer goods to another plant, after send the goods of one plant to another plant and have the billing, the stock stay in transit, so, we already have the ShpgNt in MD04 in receiving plant, and the SchLne in MD04 continues influencing directly of the future needs planning in MD04. The correctly situation is the SchLne desappear of the MD04 because I already have the ShpgNt.
Do you havethis situationand hasa solutionfor thisproblem?