Dear all,
When the description off a release code is changed, e.g. 01 Anne to 01 José. The old PR with 01 Anne can´t be approved. The system shows a message.
If I change, e.g a costs center 01 for and other 03, the RC takes other strategy 03. If I put again the costs center 01 the RC stays without ANY release strategy and the system shows a message.
For new RC the system works normally taking the strategy 01 with the new description
Someone know how to resolve the situation with the old RC with a SAP note or …
Now by procedure we approve old RC and then we transport the change of the description of the release code. But as that the support of MM (level 1 for us) is done out of the company we have always the same issue (confusion)
Cheers,
marta