Hello experts,
We switched on the "shipment Scheduling" for some supplying plants (Customizing: SPRO --> Materials Management --> Purchasing --> Purchase Order --> Set up Stock Transport Order --> Assign Delivery Type and Checking Rule).
After doing this change, we realized that when the confirmed date is not the requested one then the system assigns a delivery time to the confirmed schedule line (eket-uzeit). When having different items, the delivery time of each item is different and this is leading to a delivery split, which is not desired.
I believe there is no way to maintain a default delivery time for all items (besides from user-exits, badis...), is it? Why would SAP behave in such way?
Can we change the delivery split logic (to avoid getting the split by delivery time (eket-uzeit)? Although I think is better to change the logic of how eket-uzeit is filled during the purchase order creation.
Any ideas?