MRP Purchase Requisition Planned delivery Date from Contract

$
0
0

Dear Experts:

 

We have a situation:

We set up the auto PO including source list which assigned the contract. However we find the planned delivery date for the purchase requisition is from contract, which purchaser didn't maintain on purpose, they were copied from material master when the contract was created.  The To-be process is MRP controller will review the planned delivery date periodically and update the material master. However the contracts are controlled by purchasing department, it's not feasible to ask the purchasing to change the contract frequently.

 

Could you give your two cents about this scenario

1. any flag we can set to make the planned delivery day is from material master, rather than source list- contract

2. If using program to upgrade contract delivery date? Any suggest on update this date.

 

Thank you

 

Janey