Hi All,
I’m trying to find a solution for my problem and so far no luck. Here’s the situation:
My client orders multiple materials from one vendor and these material are being shipped in a container. The challenge here is to fill up the container.
For instance:
There are Purchase Req. for:
- 10 PC of material X
- 20 PC of material Y
The container capacity is 1 M2 (where M2 is some UoM). For both materials X and Y , 1 M2 = 60 PC.
My client wants to ship in full containers only. I tried to use rounding profile (static and dynamic), but SAP always rounds up each line separately, so I get a full container for each material (PO is created for 60 PC of X and 60 PC of Y). It should be 20 PC of X and 40 PC of Y.
I would like to know is there any standard solution so SAP will look at all items in PO during rounding?
Thank You!
Best Regards,
Marek