Dear Experts,
I have searched in SCN and different forums but couldn't find appropriate solution, so please bear with me.
I have following business requirement :-
Need to do intra company code STO (Plant A to Plant B)
Material : X
Plant A: 0001 (500 KG material X has been procured in January with price 100 INR per KG in plant 0001)
Plant B: 0002 (price of material can be 90 INR or 110 INR in April)
price control is MAP in both the plant.
Profit Center1 : 0001 for plant 0001
Profit Center2 : 0002 for plant 0002
500 KG material has been procured in January and kept in plant 0001 till April, meanwhile due to different circumstances 5 KG material got spoiled which is basically loss of profit center 0001. I have to send 200 KG material to plant 0002 for production/further process in a way so that loss would be recovered for profit center 0001. (have to increase price i.e. 120 INR per KG and send to plant 0002). (I am taking 120 INR as an example it can be any amount more than 100 INR.)
Current Process: We maintained third plant 0003 with profit center 0001, firstly we maintain price 120 INR in plant 0003 and then transfer material to 0002, so that we can recover loss in profit center 0001, (we use MR21 to change the price which is i think not correct).
(we follow 2 step STO)
However this is not standard process, but this is how our business requirement is. Please suggest any other way to fulfill this requirement
Regards
Abhishek