Dear Expert,
I have following senarion in PS during PR price change. I want to change the PR (Service) value in activity of PS.
1. when I was trying to change the PR value in PS in particular activity then the following information message was prompt and the price field was grey, and I am not able to change the PR value.
2. i did customisation in SPRO-Material Management -> Purchasing -> Environmental Data -> Define Attribute of system data-> system mesage, and change there system mesage as bellow
3.Now i am able to change the price of PR, but I dont want to change the PR( Service or Material both) Value less than PO.
4. Also release strategy should not be impacted while decreasing the value.
My concern is that I want to change the PR value for both Service or Material type, but system should not allow less price than PO value. In the current senario PR value can be modify less tha PO value whic is wrong.
Please advice any suggestion.
Thanks in advance.