Hi Guys,
I need some clarification in Consumption Based Planning. For example if i am having Material A. Total stock which is available is 90. In MM03 i have set MRP type VB- Manual reorder point.
Reorder point is 100
Lot size-HB
Maximum stock level is 1500.
Total replenishment time- purchase processing time+planned delivery time+ GR processing time which I have given as 2 days.
Purchase requisition is done automatically via MRP. And Purchase Requisition converted to purchase order initially for 400, 1000...Now on order stock is 1400 & Available stock is 90. Now when PR is converted to PO its showing 10 quantities automatically in PO. when i manually change Quantity as 20, its allowing.
But maximum stock level is 1500. Now its showing as 1510. But maximum stock level I have mentioned as 1500. Is this standard process? How to avoid manual change in Purchase Order quantities which comes via Purchase Requisition which comes automatically via MRP?
Kindly refer the screen shot.
Thanks & Regards
Subbu.