What is the outcome of setting a scheduling agreement additional data field of "Firm Zone" = to the "trade off zone"?
Currently the Firm Zone = the material lead time (77)
With Firm zone = 77
Trade off Zone = 77
AND
Binding on MRP = 1
Does this now allow changes to be created within the trade off zone (even if it equal the firm zone)??
I want to set the scheduling agreement up correctly so that changes are NOT made within the Firm Zone (lead time).
Do I still need to set the "Biding on MRP" to NULL?