Quantcast
Channel: SCN : All Content - SAP ERP - Logistics Materials Management (SAP MM)
Viewing all articles
Browse latest Browse all 6446

Project Stock in material planning

$
0
0

Hi,

 

I have a question about the project stock.

 

Project Stock is consider by MRP as part of available stock in standard SAP.

 

However, if I look at the MD04, it doesn’t seem the standard SAP take into consideration of project stock during MRP run. Please see following pictures.

 

 

A – There is a stock quantity of 115EA, and a maintenance order requirement of 300EA, and a project stock with WBS element of 120EA.

 

P1.jpg

 

B – After a MRP is run, a planned order is generated with 185 proposal.

 

P2.jpg

 

Thanks

Tuff


Viewing all articles
Browse latest Browse all 6446

Latest Images

Trending Articles



Latest Images

<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>