Subcontracing of Project stock Q

$
0
0


Hello

We have scenario for subcontracting of project stock Q. which is linked to WM (without CIN).

 

process in brief:

1.       1.PO created to account assignment Q (project stock) and L for subcontracting.

2.       2.Component requirement are entered to SLOC 9999 (material @ vendor) in PO by purchaser.

3.       3.On purchaser request Warehouse transfer project stock Q to SLOC9999 and assign BIN = Vendor and ship Q components to vendor ref to PO number.

4.       4.Vendor execute PO and deliver manefactured part number.

 

5.       5.Warehouse do Goods reciept and subsequent GI of components. (as a result of GR with PO number & item with Q+L (subcontracting))

 

ISSUE: In WM the GI do not seem to process the transfer order correct on movement type 543. A transfer order should be automatically created and confirmed for component upon GR.

How to perform this step

6.  Cancel a GR for subcontract PO and the movement 544 and the cancel GR did not cancel the component GR properly (back to plant/storag elocation 9999 and vendor bin)

 

What could be the raeson? how to solve?

 