Dear Expert,
I have set MRP type V1 as our MRP procedure (Manual Reorder Planning w/ External Requirement). The following scenario that I am facing problem;
ROP = 100
Lot Size = HB = 110
Stock available = 0
Plan Delivery Time = 45
Planning Horizon = 75 days
Sales Order #1 = 20 (Delivery Date = 15/01/2015)
Sales Order #2 = 100 (Delivery Date = 30/01/2015)
Sales Order #3 = 150 (Delivery Date = 15/05/2015)
When I run MRP on 01.12.2014 with parameters;
Processing Key = NETPL
Create PR = 1
SA Delivery Scheduling line = 3
Create MRP List = 1
Planning Mode = 3
Scheduling = 1
The system trow me result (MD04)
PR = 380 w/ delivery date 15.01,2015 (Plan delivery Time is 45)
My query is, why does the system consider all requirement even beyond Planning horizon, the result suppose to be PR = 230. Is it V1 does not consider Planning horizon and how to rectify? Appreciate any single answer, thanks.
Best regards,
M. Mahjuddin