Hello All,
In one of our project, we are migrating material consumption history data from a plant (Say plant A) to plant (Say plant B), we are doing the following,
1) Extracting entries from MVER table for plant A which is the source plant
2) Inserting them in MVER using a function module for plant B which is the target plant
3) Same material is extended in plant A and in plant B
4) The migrated entries from plant A are then shown in the consumption tab of material master header in plant B
Now the problem is that when we try and run the report MC.9 for material for which we migrated entries in MVER table from plant A to plant B, it does not show the consumption history for plant B, it shows for plant A.
We had assumed that only migrating MVER table data would solve the problem of not losing material consumption history in plant A, however in plant B MC.9 report does not work as it works in plant A.
Is there a link between MC.9 and MVER table ? If yes what all material data we need to migrate ? We want to close plant A, as it is shutting down and move all history data to plant B, however it should also show in MC.9.
Any help inputs, past experience or alternative approach suggestions would really be appreciated.
PS: I am a PP/QM consultant, however I have best tried to explain this problem, which I believe is MM related
Best Regards,
Ameya B.