Hi Folks,
We have EWM integration.
The scenario is like this:
- Our user had created a PO
- For some reason, the requirement for one of the PO line items is not there any more
- So, she tried to delete the PO line item
- However, she got an error message saying that "There is an open inbound delivery 180####### in the WMS for PO 45000#######, item *** "
- This IB delivery was not visible in either PO History tab or confirmations tab of the PO
- The qty. for the material was zero in that IB Delivery.
- Since qty. is already zero for this delivery, cancellation in EWM is not working out
There are two questions:
- Is there a workaround to delete the PO line item ?
- Why was this IB delivery created? Is there a way to avoid this situation in future ?
Thanks