Multilevel subcontracting LO_MM_OM_2 does not work...

$
0
0

Hello all,

 

I am experiencing difficulty getting the Multilevel subcontracting functionality up and running.

The Business Function LO_MM_OM_2  is activated and I have customized a Special procurement key 99 in which the Procurement key = F, the Special procurment is L, and the Multilevel subcontracting indicator (V460A-MLSCR) is ticked.

 

Next I have created two Materials (TEST1, TEST2) both with Procurement key F and Special procurement key 99.

A third Item I created is TEST3 with only a Procurement key F in it.

The BOM is: 1 PC of TEST1 consists of 1 PC of TEST2, and 1 PC of TEST2 consists of 1 PC of TEST3.

Subcontracting Infor ecords and Source lists with fixed Vendors and MRP relevance, all maintained.

 

Now when I run MRP and a Purchase requisition is created for Material TEST2, nothing special (other than normal) is visible in the Purchase requisiton with regards to the Multilevel subcontracting functionality..
According to the documentation, I should be able to see where the Material TEST2 should go (to the next subcontractor that will make TEST1 out of TEST2).

I ran report RM_MLSC_TRIGGER_MLSC_MRP for the Purchase requisitions in question, but I get the message '06158 No documents found for this selection..'

Also, when I manually create a Purchase requistion for TEST2, nothing happens other than normal.

 

Does anyone have a clue how I can solve this?

And is ther more documentation out there apart from the one in help.sap.com which is very limited.

 

Thanks in advance for any clues.

Kind regards,

Bart Jongen


Viewing all articles
Browse latest Browse all 6446

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>