Hi all,
There is an issue with the user exit key used for the MRP controller wise MRP run with MD01. We tried to run MRP for the plant with the user exit for MRP controller wise selection of materials. I have given the required MRP controller values in the selection screen. But after the MRP run, I noticed the proposals(purchase Requisition) are not created for the materials which was happening with Manual MRP Run with MD02 & MD04.please help us in this regard and the needful information follows
Regards
Lakshmanna