Plant level MRP run

$
0
0

Hi Experts...


I have 3 queries, struggling with finding solutions. All 3, regarding the MRP run.


1. There is a requirement to run MRP using MD01, but only for the uploaded PIR , not for all materials in the planning file. Is it possible? or can anybody explain the process steps please?.


2. I tested a sample scenario in ECQ with processing key NEUPL. Planning results displayed. But when i do the same with processing key NETCH, material didn't plan. Please explain the possible reasons.


3. What are steps need to follow, when we run MRP 1st time.

 

I have attached the screens for the issue no 02



Thanks & Regards;


Malka


 