Dear all,
While doing MRP run we are facing one issue in our QAS...
When we do run MRP for semifinished material on 25.9.12, system raised PR for raw material(we need to issue to subcontractor) and that PR converted to PO
PO doc date is 25.9.12 since it is subcontracting PO for the semifinished material delivery date is 30.12.12......when i check for the components system prposed the requirement date as 6.8.12......When i run MRP on 25.9.12 why system proposed rawmaterial procurement should be done at 6.8.12