Hi All,
I would like to be able to valuate a Sub Contracted Material on Moving Average Price. The material was initially set for 'S'. I changed it to V recently.
But when I post the GR for this parent material, system is still taking the valuation at Standard Price for the parent component which was subcontracted & set with V indicator in the material master.
Is it that Subcontracted materials need to be always Standard Price?
Please let me know why system is considering the Standard price in GR even though the price control indicator is 'V'. I am not getting this problem in quality system.
Kindly provide the resolution for the same.
Regards,
SAP MM.