Hi,

 

  Client is creating PO w.r.t contract which is set as "5-GR date" for Price control and the same has been set in vendor master. There is no price control set in info record "No Update". But when i check PO in EKPO table, system shows price control as 5 for some PO's and showing empty for some PO's, due to which the value is showing wrong during GR. Can you please tell me from where the price control is determined in PO? and why it is showing 5 for some PO and not showing that for some PO.

 

Regards,

Prasath J