Hi All,
Appreicate someone can enlightened me on how the MRP Planned date been generated. I have executed MRP Run with TCode MD03 with 2 material (100043873 & 100043876). Both materials have set Planned Delivery Time is 10 Days, and PRI also has the same Planned Delivery Time.
I have set both In-house production & GR processing time = 0 days.
When I check these materials via TCode MD04, I found out the Planned date is different. Please advise if you have any idea how this date being generated. Thank you.