Dear Guru,
I have an info record and contract (Outline Agreement) and which i have maintained the contract in the source list.
But when i try to create the PO via ME21N, the program is determined the info record instead of Source list with outline agreement, but if in the case for PR, it is able to determined the source list with outline agreement by click on the assign source of supply or via ME57.
Can anyone please advice me what is the reason why the PO creation via ME21N(without PR) doesnt able to auto determined the outline agreement? what should be the source determination sequence in the case of PO creation via ME21n?
Thanks and Regards
CW