Options in Contract - ME31k

$
0
0

Dear All,

 

I have following queries in Contract :

 

A.  Can we add multiple payment terms and validity perios in contracts.  We have a contract with Vendor for long time in which he delivered

      various Services and materials.

 

     There are diff. payment terms for that vendor as below

    

     1. 10% Adv. Against Service PO

     3. 50% payment after complition of 50% work i.e. services

     4. Remaining payment of Services after finishing of Services.

     4. 100% payment against PO for the materials  (whenever we issue PO  for example, out of 100 materials, if we issue 40 materials PO today

         then we will make 100% payment for 40 materials.)

 

B.  If  there is a change in service i.e. say more services are added or may service charges needs to modify.  We need to issue revised contract to vendor.

      Which process is advisable for better tracking of document flow and controls. e.g. If I create single contract then System will control that user can

      not prepare PR/PO for more Qty or Value.

    

 

Thanks and Regards,

 

Nirav