Hello Guru's,
I am working for a client that has a 2 step release strategy for PO approvals. They also have a release indicator of 6 - Changeable, new rel. if new strat. or value change/outputted.
With this setup they are able to make price and quantity related changed without any problems. The issue comes when they attempt to change anything that does not increase the overall value of the PO i.e. Delivery Date, QTY decrease.
If a date is changed then I am getting the following errors from sap:
1) Release Prerequisite not fulfilled [ME102]
2) System Error (Error in method PO_POST) [ME816]
The workaround we have in place is to increase the qty on a line and send the PO through the release strategy. Then prior to being approved the user can go in and make any changes they want and the PO will go through release strategy without error.
I have tried using every release indicator available and I am still getting the same error. I have tried using the other solutions provided by the community and nothing has been working.
Any assistance with this would be greatly appreciated.