Hi All,
In our system SAP works as;
requirement date - GR processing time = delivery date
delivery date - Plan delivery time = Release date
System consider Plan delivery time on Material master not from inforecord how can i change this ?
MD04 consider avability date as Confirmation date Of Vendor not add any tranport time , how can we solve this ?
To add trasport time to GR processing time is a method but not solve problem while i purchase one material from different vendors.